Oregon Consolidates 11 Data Centers into One Energy-Efficient Facility

Oregon Data Centers Go Green

Feb 8, 2008, By Andy Opsahl

Data centers devour more electricity than almost any other state government facility, but few states have implemented green data-center initiatives. Oregon, however, is now one of the first to do so.

On Dec. 13, 2007, Oregon announced it consolidated 11 power-hungry data centers into the Oregon State Data Center (SDC), an energy-efficient facility located in Salem.

Before switching to new equipment, project leaders moved the state's existing data center equipment into the new central facility, cutting power bills by 35 percent, according to Mark Reyer, state data center administrator for Oregon.

 
Access Pool
Among the new technologies used for this data center is a storage area network (SAN) installed to centralize data storage, rather than using hard disk drives on individual servers, which are major power drains.

"If you have four or five 300-gigabyte hard drives on a server, and you're using 50 percent of their capacity - and then you multiply that by 1,500 servers sitting in the data centers - you have a tremendous amount of capacity that is being underutilized, but can't be allocated somewhere else," Reyer said.

The SAN pools all of the data, eliminating the problem of unused excess capacity.

"This gives us incredible flexibility to have on-demand computing so we don't have oversized and underutilized assets, such as servers waiting for peak periods," Reyer said. "We can have the amount of capacity we need and be able to allocate it on an as-needed basis for the agencies and their business cycles. It's a tremendous saving of assets, as well as optimal use of power itself."

Oregon's SAN puts data in a tier system, placing frequently accessed data in the top tier. As end-users access a piece of data less often, it drops to lower tiers until it hits the bottom and moves into an automatic tape library.

The automatic tape library provides additional power savings. In the past, each group of four servers had its own tape backup system. Now, one library serves all data, using robotics to move data in and out of the library, saving IT workers the hassle of manually moving data to and from the tape library. Eventually that data travels to a state-mandated, offsite data-archive facility.

The data center also reduces power consumption by using Oregon's temperate climate to cool the facility. The system sucks in cool air from outdoors, routing it through the floors supporting the servers. Warm air, in turn, is pushed out of the building. As a result, the facility uses its water chiller only 25 percent of the year, while most other data centers run their chillers year-round, Reyer said. "Oregon is a good place for data centers, given this climate," he added.

 
Learning to Share
It took several years to persuade agencies to relinquish IT control to a centralized "shared services" model, Reyer said, adding that agencies worried a centralized model would ignore agency-specific needs. But leaders realized many of their IT functions were the same across the state.

"If it has to be customized for an agency, then it's not a shared service. However, almost everything we do is at the utility end of the IT spectrum," Reyer said. "If it's on the infrastructure end of the IT spectrum, it can be shared. Storage, computers, networks, security - those don't differentiate whether you're providing transportation services or state police services to citizens."

Consolidation and standardization reduces Oregon's need for specialized IT knowledge, which Reyer said was a relief given the projected exodus of baby boomers ready to retire. When agencies individually managed their data centers, the state worried it would need to train new employees on different systems. 

"Much of that fear has gone away because Windows Server administration is Windows Server administration," he said. "There are not too many differences from agency to agency."

Keeping with the state's energy efficiency goal, the data center also reduces power consumption in the office section of the building.

"We built our office with a tremendous amount of natural lighting," Reyer said. "The exterior and interior have metal louvers that actually take the light from the outside and direct it in."

KW

If You Liked This Article, You May Also Like...

Related Products and Services


Latest Government Technology News


Industry Solutions for Government

Read real world deployments of technology in government from our sponsors.

View All Industry Solutions

Marketplace



This section
brought to you by:


Communications and Interoperable Technology Survey

Emergency Management magazine invites you to participate in our Communications and Interoperable Technology Survey. Our 11 questions are very brief and should only take 5 minutes of your time.

Complete our survey now, and enter to win a $25 Amazon Gift Card!

Dispatch Operations and Interoperability

Webinar: A New Era in Public Safety Wednesday, December 10, 2008 from 11:00 am - 12:00 pm PST/2:00 pm - 3:00 pm EST


A New Era in Public Safety BlackBerry® smartphones running on Sprint networks deliver a wide range of applications that are transforming public safety operations.


Hurricane Preparedness Tips When a hurricane hits, are you prepared to keep in touch?


Case Study - Morris County, New Jersey The Morris County Communications Center upgraded to a new trunked radio system with the benefits of a cellular network, extending coverage beyond county lines


Case Study - Iredell County, North Carolina Spanning over 570 sq miles, it became imperative that the Iredell County Emergency Communications, Operations and Management extend it's communications systems to enhance reliability, security, and coverage.


Case Study - City of Anaheim, California The City of Anaheim saw an opportunity to leverage existing GST and partner with nearby cities to enhance safety operations through data interoperability.


Case Study - Charlottesville, Virginia Fire Department Taking advantage of a range of interoperability solution, the Charlottesville Fire Department has achieved a network that can serve as backup to their existing public safety network.


Sprint ERT Go-Kit with GST Optima Rapid, interoperable communications for emergencies, drills and field exercises.


Optimal Interoperability Until recently it was not possible to cost effectively connect commercial networks to LMR systems. Improvements in communications technology have resulted in greatly enhanced operational capability and have reduced the log-term cost of communications system ownership.


Multi-agency interoperability for Public Safety Establishing cross-agency, real-time situational awareness is critical to effective incident management as well as daily resource management.


Video


DHS Grant Links

DHS Grants and Assistance Programs Link to overview of available grants administered by The Department of Homeland Security (DHS)


Fact Sheet: Fiscal Year 2008 Preparedness Grants Major changes in funding and focus for 2008 DHS grant programs


Remarks on 2008 Homeland Security Grant Guidance DHS Secretary Michael Chertoff and FEMA Administrator David Paulison


$1.8 billion in DHS Homeland Security Grant Program Awards


Funding Public Safety Communications Whether you are a law enforcement agency, looking for funding to support an interoperable communications solution or a school, seeking to improve communications between building administrators, grants may provide the funding you need to implement a robust, scalable communication system.