MTA Demands Contractor Speak to Ongoing Train Control Debacle

New York’s Metropolitan Transportation Authority is ready to go through the process of removing the contractor responsible for the troubled installation of crash prevention technology unless the CEO appears at the next board meeting.

(TNS) — The Metropolitan Transportation Authority's board, frustrated with the installation of federally mandated crash prevention technology for the Long Island Rail Road and Metro-North Railroad, on Wednesday threatened to fire its contractor if its CEO doesn't show up at its next board meeting.

At a Manhattan meeting of the MTA, board member Laurence Schwartz told representatives from Siemens Mobility Inc. that if its chief executive, Joe Kaeser, does not attend the agency's next board meeting in May to answer questions about problems with the installation of positive train control technology and offer assurances about the project, Siemens would be "fired."

Informally polled by new MTA Chairman Patrick Foye on Schwartz's proposal, board members unanimously gestured they would support severing business ties with Siemens, an international technology conglomerate that Foye said has been awarded "hundreds of millions of dollars" in contracts by the MTA over the years.

That includes a $440 million contract awarded in 2013 to a joint venture of Siemens and Bombardier Transportation to design and install a positive train control system, or PTC, for the LIRR and Metro-North. PTC works by having the antennas on trains communicate with radio transponders installed along tracks to automatically slow down or stop a train that goes too fast or violates a signal.

The rare step of "debarring" a contractor would exclude Siemens from future consideration for contracts with the MTA.

Foye on Wednesday called the company's recent performance "shockingly appalling" and rife with "repeated instances of incompetence."

"I think they and their counterparts may take our business for granted," said Foye, adding that it would be up to the MTA's lawyers to figure out the logistics of parting ways with Siemens. "Our preferred solution is to get the project done."

Siemens officials would not say Wednesday if Kaeser, who is based in Germany, would attend the MTA meeting scheduled for May 20. In a statement, the company, which reported nearly $70 billion in earnings last year, said it is "committed to providing MTA — and all of our — customers with the highest quality intelligent infrastructure technologies that result in safe, reliable and efficient transportation for their passengers."

The latest dust-up with the contractor came after Siemens, while in the process of addressing a calibration error that resulted in the recall of about 1,000 "undercar scanner antennas" needed for PTC, realized it had made another mistake in how it was installing a related electrical component — soldering them onto circuit boards rather than bolting them, as specified by the manufacturer. The goof will require making additional repairs to the recalled antennas.

The original recall stemmed from the discovery that equipment used to test the antennas had not been calibrated in three years. Siemens officials said they also found out that the employee responsible for tuning one of the components of the recalled devices was only following the proper protocols when he knew he was being observed during quality control audits.

The MTA also has blamed the contractor for several other mishaps in the PTC project, including late-arriving and defective software and inadequate staffing. MTA officials have said despite the numerous errors — and a looming federal deadline to complete the project — the PTC contractor is not approaching the project with the needed urgency.

"I didn’t see any outrage," Foye said of a recent meeting with Siemens' representatives. "The outrage is all on the MTA's, Long Island Rail Road's and Metro-North's parts."

In a statement, Siemens officials said they are working with the MTA "to address the matter as quickly as possible and have completed a comprehensive review of the entire assembly process with engineering, quality, and manufacturing prior to restarting our production line.”

Siemens said it is also adding personnel and other resources to complete the project on time. MTA officials have said the latest blunder further sets back the delay-plagued project by several weeks.

Under the U.S. Rail Safety Improvement Act of 2008, which stemmed from a Chatsworth, California, commuter train crash that killed 25 people, railroads were required to have PTC in place by the end of 2015. When it became apparent that most railroads could not meet the deadline, federal lawmakers agreed to push it to 2018. Having encountered various delays, the LIRR last year sought and was granted another extension until 2020 to complete the project. Missing the deadline could result in fines as high as $27,904 a day.

Despite the latest glitch, MTA officials said they still expect to meet the deadline.

On Wednesday, Sen. James Gaughran, D-Northport, who has chided the MTA for allowing the various PTC problems to occur, praised the MTA for what he called "a dramatic shift in tone."

“There is an oversight responsibility that every government agency has, including the MTA, over contractors,” Gaughran said. “You’ve got to see what they’re doing, spot check what they’re doing, constantly review . . . because, if you don’t they’re going to probably cut corners.”

TIMELINE

  • October 2008: President George W. Bush signs into law the U.S. Rail Safety Improvement Act, which requires railroads to install positive train control technology throughout their systems by the end of 2015.
  • November 2013: After unsuccessfully petitioning for an exemption to the federal law, the MTA awards a $428.5 million contract to a joint venture of Bombardier Transportation/Siemens Rail Automation to design and install PTC throughout the LIRR and Metro-North. The board later increases the cost of the contract by $11.3 million.
  • October 2015: With several railroads, including the LIRR and Metro-North, saying they need more time to complete their PTC projects, the federal government agrees to extend its deadline to December 2018.
  • November 2016: Falling further behind, the MTA acknowledges it has begun installing parts of its new PTC system before the entire system’s design is complete — risking the possibility of having to undo and redo some work.
  • February 2018: The MTA discloses it has shifted its focus from completing PTC installation by the end of 2018 to meeting the minimum federal standards to qualify for an extension until 2020.
  • April 2018: The MTA reveals its PTC system failed in several test simulations on the LIRR, further setting back the project.
  • December 2018: With days to go, the MTA announces it has met the minimum federal standards to be granted an extension until 2020 to complete PTC.
  • February 2019: The MTA announces its PTC contractor has recalled hundreds of “undercar scanner antennas” installed on trains because they were not properly calibrated.
  • March 2019: In the process of repairing the recalled antennas, the contractor discovers another mistake in how a related component was installed.
  • April 2019: MTA officials demand that the CEO of Siemens come before them to answer questions and offer assurances, or risk having his company “fired.”

    SOURCE: Newsday
©2019 Newsday. Distributed by Tribune Content Agency, LLC.